Backup generators in Hanoi are part of the power sector’s planning for 2027. According to EVNHANOI, the utility has approached 198 customers with generators, totalling about 221.5 MW, to coordinate on-site power when needed. Hanoi’s peak demand in 2027 is forecast at about 6,800 MW, up from 6,290 MW in 2026.
The information comes from the conference “Solutions to ensure Hanoi’s power supply in 2027”, organised by NSMO and EVNHANOI on the morning of 18 November 2026, and from an interview of Mr Nguyen Anh Dung, Deputy General Director of EVNHANOI, with Cong Thuong Newspaper, published on 22 November 2026.
How much electricity will Hanoi need in 2027?
- 2026: Hanoi’s peak demand reached 6,290 MW at 21:30 on 26 May, up 4.97% from 2025.
- 2027: EVNHANOI prepared two scenarios. The base case has a peak of about 6,800 MW. The high-growth case, about 12% higher, reaches about 7,045 MW.
- Why demand is rising: transport projects, industrial parks, data centres, social housing and electric vehicles. Installed capacity for electric motorbikes and battery-swap stations alone is already about 220 MW.
- Weather: household use is about 65% of Hanoi’s consumption. In the first half of November 2026 there were days with temperatures of only about 32°C but demand up 21–30% year on year, and one day up almost 50%.
Will additional supply keep up?
According to NSMO, peak demand in northern Vietnam in 2027 is expected to rise by about 3,000–3,500 MW compared with 2026. Additional capacity able to support the northern evening peak is expected to total about 1,320 MW. Rooftop solar is expected to add about 1,280 MW but its direct contribution to the evening peak is limited.
Hydropower reservoirs have not stored enough water, with a shortfall equivalent to more than 2 billion kWh, so NSMO has had to dispatch oil-fired (FO) plants at high fuel cost. Hanoi’s own generation is also limited: apart from two waste-to-energy plants, solar capacity in the city has reached only a little over 200 MW.
How are backup generators in Hanoi being mobilised?
- Non-commercial load adjustment: EVNHANOI has signed up 291 customers who are ready to take part when the system asks, with two hours’ notice.
- Customers with generators: 198 customers, totalling about 221.5 MW, were approached to coordinate on-site power when needed.
- One real mobilisation: on 27 May 2026, EVNHANOI mobilised about 50 MW from 13:00 to 14:00 at the Vinhomes Smart City urban area in Tay Mo. The article does not say that all 50 MW came from generators.
- Priority list: NSMO asked EVNHANOI to review and update its list of customers by supply priority, and to do it early, even though the goal remains to avoid load curtailment as far as possible.
The sources do not state the specific terms for mobilising generators (price, running hours, how notice is given), so this article does not speculate on them. For the wider national picture, see EVN prepares for the 2027 dry season.
247Power’s view: what should businesses in Hanoi prepare?
This is 247Power’s opinion, not information from EVNHANOI or NSMO. A strained grid does not mean businesses will be cut off, because the stated aim is to avoid load curtailment as far as possible. But if your site has equipment that cannot stop suddenly, now is the time to review your on-site power plan:
- Know your real load. Generator size should follow measured load, not the nameplate rating. See how to calculate generator capacity.
- Check your existing generator before the peak. Fuel, batteries, the transfer switch and the generator maintenance schedule should be reviewed before the hot season, not tested for the first time when needed.
- Ask about the rating if the unit may run longer than planned. A unit used only for outages is different from one that must run regularly. See Prime and Standby generator ratings.
- Ask the utility before committing to load adjustment. The specific terms are set by the utility, so read any agreement carefully.
Businesses considering an investment can look at 247Power’s industrial generators or ask for design, construction and installation advice to choose a size based on the real load.
Written by the 247Power editorial team with the help of AI tools. Figures were checked against the sources above. The assessment section is 247Power’s opinion.
Head office: 316 Le Van Sy, Tan Son Hoa Ward, Ho Chi Minh City, Vietnam
Hotline : 0911 888 247 - 0888 999 247
Email : info@247power.vn